21.04.2017
The “Maturity Gate 6.1” industrialization review was held March 27 to April 20, 2017, among Airbus Safran Launchers, its industrial partners and independent experts Based on the positive outcome of this review, production of the Ariane 6 ground qualification models has been green-lighted The first flight of Ariane 6 is scheduled 2020
With “Maturity Gate 6.1”, Airbus Safran Launchers and its industrial partners have passed a major milestone in the development of Ariane 6, under contract with the European Space Agency (ESA). The review confirmed that the maturity of the industrialization of Ariane 6 is sufficient to begin production of the ground qualification models for the future European launcher, in accordance with the objectives of the program. This major step follows on from “Maturity Gate 5” which, in 2016, had enabled Airbus Safran Launchers to validate the technical, industrial and programming characteristics of Ariane 6 and to continue with development of the launcher with its partners, as planned.
The Ariane 6 development method, called “Ariane 6 Way”, comprises 15 major steps, 6 of which have already been completed. “Maturity Gate 11” will give the green light for the first flight of Ariane 6, while “Maturity Gate 15” will mark the end of development and the start of full operational capacity.
Each “Maturity Gate” takes place under the responsibility of Airbus Safran Launchers, and involves independent experts. “Maturity Gate 6.2” is slated to take place at the end of 2017, so that the production of the first Ariane 6 flight models can begin.
Ariane 6, which is also ideal for constellations, is built on behalf of the European Space Agency (ESA) and will be a flexible, modular and competitive launcher available in two versions, Ariane 62 and Ariane 64, to guarantee continued European access to space.